CAPITAL PROJECT MANAGEMENT SERVICES, LLC | |||
DINING, SERVERY AND KITCHEN IMPROVEMENTS
This project gut renovated 10,000 sq ft of existing dining & kitchen
facilities in 3 phases while fully maintaining ongoing operations. The
project involved kitchen equipment replacement, kitchen exhaust and
make-up air systems, HVAC cooling and hydronic in-slab heating in the
renovated dining area in addition to a new servery area.
The project was completed in 1995 for $1.6 million dollars which would
be equivalent to $2.2 million in 2009 dollars.
Mr. Richard Lanzarone provided Construction Management
services which included the following
services: phasing planning, communication plan,
bidding and award, schedule development and maintenance, weekly progress
meetings, submittal, sample review approval tracking, coordinating
multiple contractors & FF& E vendors, monitoring work progress, &
compliance with contract documents, applications for payment, monthly
cost reports, negotiation and approval of change orders, regulatory
approvals, move-in coordination and warranty management.
Contact:
Robert Seidman,
Chief Administrative Officer
105 Mary’s Ave
Kingston, NY 12401
845-334-4801
Archititect: Optimus Architecture
David Souers, AIA, ACHA, ASHE
187 E Market St
Rhinebeck, NY 12572
845-876-8202
Contractor: The Granite Group
James Pasciola, President
71 W Trail Rd
Stamford, Ct 06903
203-329-0157
|
|
![]()
![]() |
|
|
|||